| The
Project commissioned by British Steel Seamless Tubes called
for the safe demolition of a steel manufacturing plant located
on a 37 acre site at Wednesfield Rd, Wolverhampton in the
West Midlands.
The scope of the works included for Asbestos
Removal, Environmental Clean up, Decontamination, Demolition
and Land Remediation.
Once the works were completed, the site,
which had manufactured steel for the previous 90 years,
would form part of the British Steel Distribution, Steelpark,
comprising of warehousing, an office complex and open parkland.
British Steel Seamless Tubes took on board
Safety and Environment as the two main issues at the procurement
stage. A dedicated Closure Team was appointed, headed by
Mr. Kelvin Skidmore (see enclosure). The Closure Team visited
both Connell Brothers Manchester offices to carry out audits
and a current demolition site at ICI Research Centre, Harrogate.
Once the BSST Closure Team were totally satisfied with Contractor
competence, Connell Brothers were appointed as Principal
Contractor to carry out the works.
Due to the previous use of the site and
its proposed future use, including time scales, Connell
Brothers adopted an innovative approach to the demolition.
Cleaning operations, asbestos removal and building separation
were all executed in a planned and structured manner to
enable third party contractors to proceed with the construction
of a new office complex, formation of roadways and completion
of warehousing for British Steel Distribution.
The project was carried out in
5 phases, consisting of;
The South Bank
This area comprised of acid neutralising plants, pump house,
sub-station no. 8, water tower, 4 no. gas oil tanks, each
containing 12,000 gallons of waste residue, 2 no. LPG tanks,
caustic soda tanks and overhead pipe gantries with asbestos
lagging.
The Upper Weldless Bay
A structure comprising of part brickwork and part clad in
RPM sheeting, (hazardous material), high level crane gantries,
high level and low level pipe gantries with asbestos lagging
and Sulphuric Acid tanks.
Engineers Stores
A two-storey structure of brickwork construction, located
adjacent to the public highway (Required the implementation
of a road closure to carry out the demolition). The building
also included high level pipe gantries with asbestos lagging,
below ground asbestos pipework with Blue Asbestos, asbestos
insulating panels to offices, cement bonded asbestos sheeting
to the roof, oil storage tanks and oil interceptor tanks.
Office Complex
A two-storey L-shaped office complex with asbestos panelling
throughout. Adjacent to this structure was a workshop/garage
with below ground fuel storage tanks.
Continuous Mill
A structure of part brickwork and partly clad in RPM sheeting
(hazardous material), sub-station, compressor house, waste
heat boiler house and chimney stack, re-heat furnace and
stack, primary sub-station, descaler pump house, transformer
pens, scale pits, stockyards with overhead gantries, high
level pipe gantries containing asbestos and high level steel
gantries with an accumulation of Graphite dust built up
over many years.
All the works were carried out in accordance
with CDM Regulations, with Health and Safety plans being
written for each phase of the work, supported by detailed
Method Statements, Risk Assessments and COSHH Assessments.
All supporting documentation in respect of the hazardous
waste disposal was also integrated into the Health and Safety
file.
Connell Brothers employed a strict regime
of the site clean up in respect of all the hazardous materials.
Asbestos materials were removed in controlled
conditions employing trained operatives, fully equipped
with the relevant safety equipment and the latest decontamination
facilities. Background monitoring was carried out as the
works proceeded and clean air certificates issued at completion
of every stage. All asbestos material was disposed of in
lockable containers to the designated licensed tip with
the appropriate documentation.
All personnel employed on site carrying
out cutting operations to steelworks (hotworks), were registered
with the BSST Safety Manager and attended regular medical
examinations by BSST appointed independent Doctor to monitor
Lead in blood levels. All operatives involved with hotworks
were fully equipped with PPE and RPE.
All residues of fuels and chemicals were
pumped out of the storage vessels using vacuum systems,
the vessels cleaned out and certification issued prior to
the substances being tankered off site to their designated
licensed waste disposal site. All acid tanks were neutralised
prior to any works being carried out on them.
The disposal of the Graphite dust that
had accumulated on steel work supports required the employment
of vacuuming techniques at high level with operatives wearing
full body and respiratory protection.
The whole of the ground floor slabs to
all structures were cleaned of contaminants by high pressure
jetting. These included heavy deposits of oil, grease, millscale,
pigeon droppings and the like, prior to the removal of the
roof and exposure to the weather.
All pits and voids were cleaned in the
same manner to the satisfaction of the BSST Engineer. Any
pits and voids not easily accessible for future filling
with recycled material were grouted. The area of these voids
amounted to 900 cubic metres.
Trial holes were excavated in and around
the South Bank area of the site and left open for monitoring
by an external third party for levels of contamination on
site. Once levels had been confirmed as acceptable, the
trial hole pits were backfilled as requested.
The demolition work was carried out using
specialist tracked excavators with full cab protection and
fitted with specialist attachments. (Steel cutting shears,
concrete pulverisors, grapples etc.) The works were carried
out using a Caterpillar 235D 70-tonne, long reach excavator,
two Hitachi 40-tonne FH400 excavators, three Hitachi FH220’s
and two Hitachi FH200’s.
All the remaining materials arising out
of the demolition were recycled as part of the BSST specification.
All steelwork was transported to British Steel Sheffield
as part of the British Steel recycling programme. All brickwork
and concrete was suitably processed on site for the filling
of pits and voids including site levelling.
Throughout the 12 month contract period,
the BSST Closure Team implemented a strict daily check procedure
and from over 300 checks carried out, no major non-compliances
were recorded.
The contract was completed on time, according
to budget, without any major accidents and to the satisfaction
of the Closure Team as demonstrated in the letters enclosed.
CASE
STUDIES - HOME
- EMAIL
|