|
After weeks of careful planning
by Connell Brothers March 2003 saw the beginning of the
end for the stadium at Filbert Street, which was the home
of Leicester City Football Club. The stadium located in
the heart of Leicester included restrictive boundaries to
all elevations and necessitated a very tight programme.
Restrictions included densely populated
terraced housing, adjacent nurses home for the local hospital
and local primary school. Further restrictions to the south
west elevation included over head pylons supplying electricity
to the former power station site and the open car park used
daily by residents and in match days by the new Leicester
City Stadium.
One of the key elements to the success
of te project was to reduce and minimise the environmental
impact on the local community. Liaison with all parties
played a key role in the success of the project. Prior to
commencement letters were issued to all property occupiers
informing of the proposed works and inviting them to attend
a Residents Consultation Meeting held at the local primary
school. This meeting explained key stages of the proposed
works and issued key telephone numbers to residents in the
event of any queries or complaints. This meeting was further
followed up with regular progress bulletins to the residents.
With preparatory works completed the demolition
project began in earnest with opening up works to enable
asbestos removal and soft strip operations. As part of these
operations Connell Brothers removed two sub stations which
were located within the grounds of Filbert Street Stadium.
All heavy demolition plant was delivered
to site out of hours to avoid congestion and inconvenience
to other road users. The CIS Stand due to its height required
the use of a specialist 100 foot cherry picker to enable
the de-cladding of the structure.
Access to the stands adjoining the rear
of the gardens of terraced properties was negotiated via
the party wall agreements put in place for the project.
Once all the structures had been skeletised the specialist
high reach machine moved in to cut down the structures using
steel cutting shears.
Each stand was demolished in a specific
sequence as detailed in the structural engineers appraisal
to avoid possible unintentional collapse.
With the older three stands demolished
the final stage of demolition works turned towards the recently
constructed Walkers Stand. The Stand comprised of a steel
work frame with reinforced concrete infill forming the terraces
and leisure/bar facilities within.
Following the structural engineers assessment
of the large stand, the structure was deconstructed in a
planned sequence employing the use of 110 foot high reach
machine equipped with concrete cutting shears and steel
cutting shears.
In line with Connell Brothers environmental
policy for sustainable materials apart from the hazardous
asbestos waste and the soft strip material all other waste
arising from the work has been recycled.
The final stages of crushing of all the
concrete to 6F2 grade was then carried out with stockpiling
for reuse on the proposed new development.
Throughout the works the Health and Safety
Executive paid several visits to site and noted no non-conformances
with the practices being adopted. The work was successfully
carried out without any injuries to personnel, members of
the public or damage to any of the properties adjacent to
the work.
The demolition was the first phase of a
£30 million project which form part of the redevelopment
of the area being carried out by Downing Developments
PEOPLE INVOLVED
Client: George Downing Construction
Project Management: Dears Brack
Contractor: Connell Brothers Limited
Planning Supervisor: Symonds Group
CASE
STUDIES - HOME
- EMAIL |