|
The
project scope called for the safe demolition of the former
Penicillin manufacturing plant, taking account of it’s
previous use, location and live services within a live manufacturing
complex.
The three-storey building was the birthplace
of the very first penicillin made at Ulverston. The three-storey
structure posed a number of challenges to the demolition
team. The building was located within the pharmaceutical
manufacturing site in a designated flame-proof area and
within a confined space bounded with live pipe gantries
and services. There was also the additional hazard of the
solvent recovery tank farm being located adjacent to the
building. Prior to commencement of works, all our operatives
attended the Glaxo Wellcome site induction course covering
the Special Site Rules for flame-proof areas.
Due to the location of the building in
relation to the pharmaceutical plant, permits to work had
to be obtained prior to commencing operations each day.
A strict controlled method of demolition/dismantling had
to be employed. Once the building had been decontaminated
and deplanted, operatives fully equipped with personal protective
equipment, (PPE), proceeded to remove asbestos insulating
boarding to the building internals working in controlled
conditions. Once all internal boarding was removed and clean
air certificates issued, external works commenced. Operatives
began to proceed with the removal of the cement bonded asbestos
sheet cladding, which enveloped the roof and external walls
of the structure.
Working from access platforms and equipped
with full PPE, operatives removed fixings securing the sheeting
using protective hand held tools, minimising any potential
danger from sparking. The cement bonded asbestos sheets
were removed in whole sections, removing the risk of airborne
contamination, and placed in sealed containers for disposal
at a licensed tip facility.
Once the task of de-cladding the building
was completed, the second stage of dismantling involved
the removal and disposal of redundant pipe-bridges and pipe
gantries. Operatives traced and identified the pipe-work
for removal. Once traced, the pipe-work was isolated, drained
down and purged of residues. Cold cut methods were employed
for the removal of the redundant gantries and pipe-work.
All works around building 10 had to be
phased throughout to allow tankers access to an off-load
point directly adjacent to the demolition area. Glaxo Wellcome
instructed that access for tankers must be maintained at
all times during the works. All vehicles and plant movements
through the site had to follow designated routes due to
overhead obstructions such as pipe gantries.
Once all the preparatory works had been
completed, Connell Brothers employed the use of the CAT
235D (70t) long reach excavator, equipped with 360' rotational
cold-cut shear, to demolish the remainder of the structures.
The long-reach excavator commenced to sectionally cut through
the steel structure placing manageable sections on ground
level.
A second Hitachi 270, equipped with shear,
assisted with further processing of the steel work for loading
and transporting off site. Due to the restrictions of the
site working space, all debris arising from the work had
to be removed intermittently to allow the work to progress.
The long-reach machine proceeded with the demolition/dismantling
of the three-storey structure, working methodically from
roof level down to floor level and completion.
CASE
STUDIES - HOME
- EMAIL
|