|
Connell Brothers of Manchester
have recently completed the demolition of 7 Multi-Storey
1960’s Tower blocks in Hattersley, Hyde. The Contract
is the largest demolition project ever awarded by the City
of Manchester.
The tower blocks form part of the Hattersley
over spill estate owned by the City of Manchester, but located
in the adjacent Metropolitan Borough of Tameside.
Connell Brothers adopted an innovative
approach to the demolition of the seven blocks by employing
varying methods of demolition.
Two blocks, Sandybank Court and Chapman
Court were demolished using a specialist highreach excavator,
capable of working to a height of 41 metres.
Due to the location of Fields Court, situated
25 metres from the main line Railway station and adjacent
residential properties 8 metres away, Connell Brothers demolished
the tower block employing the floor by floor deconstruction
method.
With the remaining four tower blocks (Underwood,
Honiton, Hattersley and Waterside Courts) Connell Brothers
adopted the explosive method of demolition. Prior to commencement
of any work on site, extensive preparatory works had to
be carried out.
With the seven Multi-storey blocks being
scattered over the estate, security fencing, 3.8 metres
high and totalling 1200 metres in length was erected for
protection of the public. 24hr patrolling security was also
put in place.
Having remained empty for some period of
time, the blocks and had become the roost for pigeons and
this therefore necessitated an environmental clean up and
decontamination operation requiring the removal of extensive
amounts of pigeon droppings.
Teams of Operatives equipped with full
PPE including disposable overalls breathing apparatus and
decontamination facilities, dampened down the droppings
with a fine mist spray of "Ornikill" disinfectant
to prevent the escape of airborne spores. The droppings
were collected, and double bagged prior to disposal as special
waste.
Once decontaminated, teams of operatives
commenced the removal of Asbestos to all seven blocks.
Representatives from Manchester City Council "Environmental
Hazards Unit" carried out daily site monitoring ensuring
compliance with legislation.Upon completion of Asbestos
Removal works clean air certificates were issued which enabled
the demolition to commence in earnest.
During the course of the works over 50
skilled operatives were employed on the project including
5 explosive engineers.
The 4 blocks demolished by explosives were
spread over a huge area of 1km by 0.5km with low-rise housing
between. This necessitated the largest ever UK demolition
evacuation, involving more than 1200 residents from 405
properties.
Close liaison was a key factor in ensuring
the successful outcome of the project. Connell Brothers
attended meetings with the client, police, local Housing
Dept, Statuary Authorities, Local steering groups and public
meetings to keep all parties informed on the procedures,
planning and phasing of the works and the sequence of events
on the day of blowdown. Liaison also had to be carried out
with numerous departments within Tameside Metropolitan Borough
Council in whose authority the estate was located.
Further negotiations & approvals were
also sought from the Civil Aviation Authority due to the
site being located on the incoming flight path to Manchester
International Airport.
On Sunday 22nd April 2001, with months
of preparatory work completed, the area was evacuated, with
50 sentries and 26 police officers lining the perimeter.
12. noon saw the successful demolition of the four tower
blocks.
Commencing at the North elevation of the
site and with a 3-second delay between each block, Underwood,
Honiton, Waterside and Hattersley Courts were successfully
brought down in sequence.
The explosive demolition required the use
of 80kg of explosive and 2400 non-electric detonating charges,
reducing the four blocks to 32,000 tonnes of rubble.
Once the areas and adjacent properties
had been inspected, clean up works were completed and residents
were allowed to return to their homes. The debris arising
from the demolition works was approximately 56,000 cubic
metres, all of which was processed on site for re-cycling
and re use.
The project, which has taken over 26 weeks
to complete, was carried out without injury to staff or
members of the public.
CASE
STUDIES - HOME
- EMAIL
|