|
Connell
Brothers were contracted by The Home Office to carry out
the asbestos removal, demolition & enabling works at
Bedford, in preparation for the construction of a new Immigration
Detention Centre.
The 25 acre demolition site was located
within the 164 acre operational Ministry of Defence DERA
site in Bedford. Throughout the project, all personnel had
to comply with MOD security arrangements and access had
to be maintained for all other site users.
Once the services had been successfully
disconnected, and prior to the commencement of demolition,
the works area was fenced off by installing 2000 metres
of 2.4M high chain-link fence with welded mesh panels to
BS 1722 pt 10. This also included for the supply and installation
of 2 electronic, card controlled turnstiles to control access,
and CCTV to monitor access positions – these being
operated by a security control point 600 metres away from
the gates which necessitated the installation of ducting
and cabling.
Further fencing had to be erected to areas
containing 90 trees which were subject to Tree Preservation
Orders and required protecting throughout the works.
Trained operatives carried out the removal
of asbestos materials from the structures, with monitoring
being carried out by The Home Office appointed Independent
Analyst. The majority of the buildings were constructed
in 1950’s and contained cement bonded asbestos sheeting.
A planned sequence of work was established to enable teams
working off access platforms to de-clad several buildings
at a time, to allow demolition to proceed.
In total, the demolition required 20 no.
buildings to be demolished with their slabs and foundations
removed. All slabs and foundations were further processed
on site through the crushing plant and all voids backfilled
with the remainder being stockpiled on site for use by the
construction contractors.
During the course of the work, a second
stage archaeological survey was carried out by the Home
Office appointed archaeologist.
Once the demolition was completed and underground
structures removed, Connell Brothers proceeded to remove
all roadways within the 25 acre sit in preparation for development.
During the course of the works, a full
drain survey of the site and surrounding area was carried
out. Due to the location of some drains, off-road vehicles
had to be employed. In total, 5,800 linear metres of drainage
was traced and plotted with the relevant information being
issued to the Home Office.
CASE
STUDIES - HOME
- EMAIL
|