|
Connell
Brothers were appointed by Client’s Lafarge Cement
UK to demolish their redundant depot situated in Widnes,
Cheshire. The project involved mainly the demolition and
site clearance of six 1500/2500 ton cement silos and other
associated buildings including two steel silos. Great care
and attention had to be given to the surrounding land users
throughout the project. A café was situated at the
depot entrance, to the west were railtrack sidings and the
surrounding land to the south was owned by Tanhouse Garage
Limited. It was for these reasons that precautions had to
be taken to prevent nuisance and inconvenience to the owners
of these premises and to the public in general. One of the
main areas of concern due to the inner concrete cement make
up of the structures and also because of their sheer height
was dust.
It was for these reasons that Connell Brothers
incorporated the use of various control measures. The silos
were initially pre cleaned prior to demolition, then a jet
powered water spray was fitted to the boom of the specialist
long reach excavator in order to suppress the levels of
dust throughout the works. This was done in conjunction
with the use of a banksman working along side the machine
driver and led to levels of dust being kept to a minimum.
Further background re assurance monitoring was also conducted
by Connell Brothers independent Health and Safety Advisor.
The project also called for careful removal
of dangerous asbestos substances namely Asbestos sheets,
gaskets and floor tiles. Connell Brothers adopted a professional
approach adhering to the guidelines set out in HSG 210 &
213 – "Asbestos Essentials" and HSG 189/2
– " Asbestos Cement."
The Management called for regular Safety
Audits of the site, weekly Tool Box Talks with regards to
safety, regular Method Statement Induction courses for all
Operatives on site, fortnightly Progress and Safety Meetings
with Lafarge. Regular auditing was undertaken to ensure
that the Project Management procedures were followed. The
9 week Project was completed on time to the client’s
full satisfaction with no injuries, accidents, or incident
to members of staff or the public..
CASE
STUDIES - HOME
- EMAIL
|