|
Chemical
Removal, Asbestos Removal and Demolition of the Former Dunlop
GRP Processing Site, Manchester.
The project requirement called for the
demolition of the former Dunlop manufacturing plant located
in the City Centre of Manchester. Built at the turn of the
century, and having been added to throughout the years,
the structure ranged from 2 to 5 storeys The site is divided
by a meandering culvert containing the River Irwell, which
caused restrictions on the movement of plant. The site is
bounded to the north by the high level platform of Oxford
Road Railway Station complete with train electrification
gantries. To the East lies the head office and computer
centre of Swinton Insurance plc with multi-storey student
accommodation for Manchester University lying to the South.
Site access was from Cambridge Street which lies to the
West. All occupiers of the adjacent properties have been
kept informed of the key stages of the project including
weekend scaffolding erection and traffic movements.
Prior to commencement of the works it was
necessary to carry out a full chemical survey in order to
identify over 300 chemical drums which had been left on
the site. These required classifying, re-packing and disposal
under special waste regulations.
The pre-works asbestos survey also identified
further areas of asbestos which had not been highlighted
in the original survey.
Following the removal of all chemicals
and asbestos, preparatory works were undertaken to plot
the course of the river culvert in order to form demarcation
lines to prevent the encroachment of any plant.
Possessions were negotiated with Railtrack
and the diversion of overhead cables was arranged in order
to carry out the demolition of the 5-storey section adjacent
to the station platform.
On the completion of the preparatory works,
the mechanical demolition was allowed to commence in a phased
sequence. During the course of the works, a number of 10
m x 3 m below ground storage tanks were discovered. These
required the removal of residues, cleaning and the issuing
of gas free certificates.
Following reduced level excavation across
the entire site and pile probing to allow for future development,
the project was completed in January 2001.
CASE
STUDIES - HOME
- EMAIL
|