|
Connell
Brothers have dramatically changed the skyline on the approach
to Manchester International Airport with the demolition
of Lodge Court, a 9-storey tower block.
Clients, Willow Park Housing Trust, appointed
Connell Brothers to demolish the 40 year old block located
on Brownley Rd and Hollyhedge Roundabout.
The demolition project is part of Willow
Park Housing Trust’s £100 Million plus programme
to regenerate the area over the next ten years.
To mark the occasion of letting the largest
demolition contract to date, Willow Park Housing Trust arranged
a photo shoot with all parties involved. These includedWillow
Park’s Management Team, Willow Park Local Residents
Group, Manchester City Architects who are supervising the
works, and Connell Brothers Demolition Contractors.
Pictured is Sharston Councillor & former
Lord Mayor, Hugh Barrett and centre right is Willow Park
Housing Trust Chief Executive, Mervyn Jones.
Councillor Hugh Barrett said, "These
flats had passed their sell-by date. Demolishing them is
a great opportunity to improve the appearance of the area
and attract new investment."
Prior to commencement
of demolition works the 9-storey structure required decontaminating.
Trained Operatives carried out the removal of Asbestos throughout
the structure in conjunction with the City of Manchester
Environmental Unit.
Decontamination of
Pigeon droppings was also required due to the building lying
empty for some time prior to demolition. Once decontaminated,
the soft strip operation was allowed to proceed.
The Multi-Storey Block was located on a
busy roundabout with adjacent occupied housing blocks only
12 metres away and a live open Substation 4 metres away.
Taking account of the proximity of the
adjacent Substation and housing, it was decided to employ
2 differing methods of demolition - Floor by Floor Deconstruction
at the sub-station end followed by Super Longreach Demolition
for the remainder.
The preparatory works included for the
total encapsulation of the Substation with protective Scaffolding
and provision of Crash Decks.
Once completed, the Gable end of the structure
and returns were fully scaffolded on the nine floors and
enclosed with Monoflex Sheeting.
Preparatory works also included for exploratory
trial holes to the floors to determine the level of reinforcement
for incorporation in the structural calculations for the
back propping arrangements.
Once the structural calculations were verified
by the Client, Connell’s backpropped the 9 floors
and, with all other preparatory works in place, two 3-tonne
excavators were craned up to roof level to commence the
Floor by Floor Deconstruction.
The 3 tonne Mini Excavators worked down
until the first 25% of the structure was removed. Throughout
this section of the work, Connell’s Longreach Machine
assisted with the separation of the 2 phases a floor at
a time.
Once the end section of the building was
removed and access created, the Cat 235D Longreach equipped
with rotating concrete shear munched down the remaining
75% of the structure in a Floor by Floor sequence.
Throughout the project, Connell Bros. provided
a Resident Liaison Officer to deal with any queries or complaints
that may have arisen out of the works.
No complaints were received and Willow Park Housing Trust’s
Chairman complimented Connell Bros. on the way the demolition
was successfully completed.
The 18 week Project was completed on time
with no injuries or accidents to members of staff or the
public.
CASE
STUDIES - HOME
- EMAIL
|