After
weeks of careful planning by Connell Brothers November 2003
saw the beginning of the end for the stadium at Maine Road,
which was the former home of Manchester City Football Club.
Along with the steel girders and masonry
a million memories will come tumbling down over the next
few months as Connell Brothers highly trained Demolition
experts reduce this precious part of Manchester City’s
History to dust with their army of state of the art demolition
machines.
The project is being carried out on behalf
of Manchester City Council to make way for the multi million
pound regeneration of the Moss Side area of the City following
the club’s move to the new stadium.
Connell Brothers are well versed and experienced
in the field of Stadia Demolition following the successful
demolition of Filbert Street, the former home of Leicester
City F.C which was completed in the summer of 2003 accident
and incident free.
This complex seven month project includes
for asbestos removal, soft strip, demolition, crushing of
materials and a reduce level dig. The package has presented
numerous challenges such as the adjacent terraced properties
and St Edwards R.C. school which is in close proximity.
Liaison and planning are key elements to the safe execution
of the works and monthly Residents meetings are being attended
to reassure the locals that Safety is of paramount importance
to Connell Brothers and will not be compromised in any fashion.
Further challenges facing Connell Brothers
have included the high levels of media interest in the project
which resulted in the incorporation of various press days
within the programme to allow access for film crews and
journalists onto site. Also prior to commencement there
was a large scale auction of various items of memorabilia
and souvenirs to the public.
The programme has further constraints in
the sense that the sequence of demolition has had to follow
a strict pattern in order to maintain the use of television
aerial equipment which is located on the Platt Lane Stand.
The Pattern of demolition has been specified as North Stand,
Kippax, Maine Stand and Platt Lane thus Connell Brothers
have had to carefully consider their approach to the works
in the light of this fact.
With preparatory works completed the demolition
project began in earnest with opening up works to enable
asbestos removal and soft strip operations.
All heavy demolition plant was delivered to site out of
hours to avoid congestion and inconvenience to other road
users. Extra care was also taken to avoid school start and
finish times
Prior to the main structural Demolition
oxy propane hot works will be undertaken to pre-weaken the
structures. Each stand was demolished in a specific sequence
as detailed in the Connell Brothers structural engineers
appraisal to avoid possible unintentional collapse.
The demolition of the stands especially
the 30m high Kippax Street (seen left) has required the
utilising of a variety of modern day demolition equipment
including the addition of a new state of the art high reach
excavator equipped with specialist hydraulic attachments
increasing Connell’s fleet of high reach machines.
This Demolition Machine reaches a staggering 41 metres and
is recognised as the largest Demolition Caterpillar within
the U.K reflecting Connell Brothers position at the cutting
edge of the industry. It was decided to tackle the Kippax
from one end thus ensuring that the bracings at the extreme
two bays at each end of the cantilever roof structure maintain
lateral stability throughout its demolition.
The Maine Stand has also presented unique
challenges due to its construction. The cantilever roof
structure is being supported by the top boom of a large
span lattice girder and will also be best approached with
a high reach shear equipped excavator. The supporting lattice
girders may be cut and toppled following the removal of
the cantilever roof structure.
In line with Connell Brothers environmental
policy for sustainable materials apart from the hazardous
asbestos waste and the soft strip material all other waste
arising from the works will be recycled.
The final stages of crushing of all the
concrete to 6F2 grade will then carried out with stockpiling
for reuse on the proposed new development.
During the course of the project Connell
Brothers will undertake a strict regime of Health, Safety
and Environmental auditing of the works with regular visits
from external advisors to ensure that it runs to programme
without accident or incident and maintains the company’s
enviable blemish free Health and Safety Record. The contract
is also accredited to the Considerate Contractors scheme.
PROJECT TEAM
Client: Manchester City Council / English Partnerships
Project Management: Davis Langdon Everest
Contractor: Connell Brothers Limited
Planning Supervisor: Faithful and Gould
CASE
STUDIES - HOME
- EMAIL |