| Connell
Brothers have currently completed a contract to demolish
the Maths Tower at The University of Manchester. The building
is believed to be the largest to have been demolished in
the city and is the latest in an impressive portfolio of
City Centre Landmark demolition contracts completed by the
company. !
The unsightly design of the Maths Tower
situated on Oxford Road in the City Centre is said to be
based on that of a scale ruler. The building was earmarked
for redevelopment following the merger last October of the
University of Manchester and UMIST to form a single University.
The Building stands at 21 storeys and is
situated within the confines of the live University Campus
which is recognised as the biggest institution in the country
and the largest in Europe with over 33,500 students. Coupled
with this is the fact the Tower Fronts onto one of the busiest
roads in the City Centre.
Due to the highly sensitive location of
the project stringent measure have had to be implemented
to control noise, dust and vibration. The Tower is surrounded
by occupied lecture theatres, libraries and auditoriums
thus it is imperative that the work is carried out causing
the minimum of fuss and disturbance to those studying inside
as well as the general public and traffic on Oxford Road.
Careful planning and Liaison are also playing
a crucial role in the smooth running of the contract. Working
closely with the University, City Council, Greater Manchester
Passenger Transport Executive is essential. Regular safety
and progress meetings are held with numerous departments
within the University to alleviate any concerns that they
may have as the works proceed.
The irregular profile of the building meant
the erection of the scaffolding was a challenge in itself.
Once the building was fully scaffold Monarflex sheeting
was fitted to fully enclose the structure and thus minimise
the effect of dust. Once the soft strip had been completed
and the Asbestos Removal Team had removed all asbestos the
main demolition was commenced.
Using a mobile crane 3 – tonne mini
diggers were lifted to the top floor of the Tower in preparation
for deconstruction floor by floor. The excavators are equipped
with hydraulic shears and breaker attachments. The are working
progressively from the roof down crunching the concrete,
and cutting the rebar which is dozed down the decommissioned
lift shafts at regular intervals. Once at ground level the
material will be taken away for further processing and recycling.
The concert will be crushed into aggregates which will then
be used on the new development.
Once the Tower has been reduced to a suitable
height from ground level it will then be attacked by a Specialist
High Reach Excavator with pulverisor attachments which will
the bring the remainder down to ground level.
A further complication to the project was
the removal of a concrete ramp that joined the Maths Tower
to the neighbouring Kilburn Computer building which proved
to be a delicate task. Connell Brothers had to construct
a scaffold to access the ramp to detach it by hand from
the Kilburn building without causing any damage to the remaining
structure. Only once the team had worked the ramp back around
3 metres from the building was it possible to advance with
main mechanical demolition.
As the nerve centre for much of the University’s
computer power, The Kilburn Building offers another test
to Connell Brothers. The ground surrounding the tower is
dense with telephone and fibre optic cables as well as gas
main, electric line and other services. Due to the nature
of the plant involved with the project it was vital that
a full audit was carried out to relocate service ducts that
could otherwise have been damaged potential knocking out
computers and other supplies across the campus.
The vast experience of city centre projects
carried out by Connell Brothers is paying dividends. The
site supervisor in charge of the site Mr Denis Cole said,
“Each time we do one of these jobs, we learn a little
bit more. Our last contract in the city was the Eagle Star
Building. It had the Metrolink Tram Line running alongside
it, so we had to work around that. Most of the operatives
on site are long – term employees so they have worked
together on many projects and have learned valuable lessons
on the way”.
Other Manchester City Centre Projects
Following the IRA bomb of 1996 Connell Brothers brought
down the Marks and Spencer’s store that bore the brunt
of the blast earning the company the prestigious “Demolition
Contractor of the Year Award. Since then it has also knocked
down the iconic Hacienda night-club, Bernard House (an 8
storey shopping complex), The Eagle Star Insurance Building,
and Maine Road The former home Manchester City Football
Club completed last year.
CASE
STUDIES - HOME
- EMAIL
|