| CONNELL
BROTHERS, having successfully completed the first ever demolition
of a post-tensioned, pre-stressed beamed building at the
former bomb-damaged Marks & Spencer complex in Manchester,
are now leading the way with the demolition of Bernard House
in Piccadilly, Manchester.
The project comprises of the demolition
of Bernard House, a 10-storey, concrete structure with a
further one and a half storeys to sub-basement level.
The building, a popular landmark in the
centre of Manchester, has a unique roof which makes it a
striking feature of the Manchester skyline. It is a timber
structure of hyperbolic paraboloid form, comprising of a
main rib element on each of the four axes of twin Glulam
Beams. Each of these is formed in turn by two Glulam Beams,
which are piggybacked and bolted together. The beams are
then boarded and weatherproofed.
As seen by members of the public, the office
structure rises above car deck level on a 9.75m square core
and a post-tensioned, pre-stressed concrete slab cantilevers
out to form the 24.4m square office floor plate. The cantilever
slab, which is 1.5m thick at its root and 535mm at its edge,
also supports the six levels of office floors and the roof
above, through the reinforced concrete mullions located
at 2.44m centres around the floor perimeter. During the
construction of the slab, one hundred pre-stressing cable
ducts were incorporated to receive the 7200, 0.276 inch
(7mm) diameter pre-stressing wires, 72 wires in each duct,
and temporary shuttering put in place as support. The cable
ducts have been laid in a longtitudinal and latitudinal
pattern producing a strong post-tensioned, pre-stressed
concrete annulus around the core (which can be likened to
a square doughnut). At three specific stages during the
construction of the upper floors, the cables were tensioned
and grouted up, allowing removal of the temporary supports
and completion of construction.
The main objective of the project is to
allow the safe demolition of the building by releasing the
loads in the cables in a sequenced manner by employing the
reverse of the construction phase. Connell Brothers will
again be working in close liaison with Consulting Engineers,
Allott & Lomax, in carrying out the exploratory works,
monitoring of cables and their sequenced cutting allowing
staged destressing. Preparatory works are currently being
put in place by fully scaffolding Bernard House prior to
removal of the hyperbolic parapoloid roof structure. Further
preparatory works underway include the back propping of
the upper floors, allowing the siting of plant at those
levels.
Due to the location of the works, a planned
sequence of weekend road closures has been implemented along
York Street to allow for excavators to be craned up to roof
level to deconstruct the building floor by floor. The Project
Director appointed for the demolition is Mr Barry Connell,
who is well experienced with city centre works, having overseen
the demolition of the former Marks & Spencer complex
in Manchester which earned Connell Brothers the prestigious
ward of Demolition Contractor of the Year.
CASE
STUDIES - HOME
- EMAIL |