| Connell
Brothers have recently completed the dismantling, demolition
and disposal of redundant switchgear, structures and buildings
within the 132 Kv Substation open compound on behalf of
United Utilities in Rochdale. The substation has been replaced
with a new GIS Substation building, which was located in
close proximity. You can see it here at the rear of the
site.
Connell Brothers are well versed in such
projects having previous experience stemming from their
demolition of a 132Kv sub station on behalf of United Utilities
at BNFL, Sellafield in 2002. Connell Brothers adopted the
same proven methods of work from this contract.
Prior to commencement of the contract separate
works were carried out for the installation of numerous
underground cables, both direct buried and ducted in concrete
cable trenches. Connell Brothers had to identify all cable
routes and provide adequate protection before any demolition
could take place. The site was also located within a National
Grid substation where there was no physical demarcation
between the National Grid and the Redundant United Utilities
Electricity circuits. Connell Brothers operations where
thus faced with compliance to both the United Utilities
Electricity Safety Rules and National Grid Safety Rules.
All works carried out within the existing
live substation had to be carried out under the direct supervision
of an authorised safety standby man who was permanently
present during the course of the works.
Further restrictions were met in light
of the fact that a minimum 2m corridor had to be maintained
around the site fencing to prevent the inadvertent provision
of climbing aids.
Throughout the works Connell Brothers demonstrated
a cautious approach to site working conditions, especially
safety by preparing and implementing detailed Method Statements
and Risk Assessments.
Due care and diligence was provided for
the on site workers and also the close proximity of residential
properties meaning all plant was equipped with silencers
and planned procedures for the damping down of dust were
also put into place.
During the course of the works Connell
Brothers were also faced with the removal of hazardous materials
such as residual oil in electrical pant, Asbestos Products
in the control room and cable basement, acid in redundant
batteries, and air conditioning coolants. All materials
were safety removed from site and disposed of in accordance
with the current legislative requirements. Careful methods
also had to be developed and approved to deal with the risk
from broken porcelain which arose fron the redundant insulator
stacks.
Connell Brothers displayed technical expertise
in demolition techniques, successful integration into a
highly regulated project environment, and full co –
operation with all systems and procedures on site.
Connell Brothers undertook a strict regime
of Health Safety and Environmental auditing in conjunction
with United Utilities throughout the contract. With regular
visit from external advisors and with detailed planning
and liaison with all parties involved it was ensured that
the demolition ran to programme and was completed without
accident or incident allowing Connell Brothers to maintain
the company’s enviable blemish free Health and Safety
Record.
The project Director appointed for the
demolition was Mr Jim Connell, who has recently gained associate
memberships status of The Institute of Demolition Engineers.
Jim is well versed and experienced contracts of this nature
having previously successfully completed the Sellafield
Sub Station.
CASE
STUDIES - HOME
- EMAIL
|