| Connell
Brothers have expanded on their experience of working within
the confines of live university campuses following their
recent contract at The University of Central Lancashire.
The Four Storey Kendal building and the
adjacent single storey asbestos clad engineering building
were demolished to allow for the installation of a new fire
escape staircase and the construction of a car park at the
Preston Campus, as part of a multi million pound redevelopment.
The Kendal Building was one of the original
Preston Polytechnic buildings built in the early 1960’s.
It was originally a three storey structure built using many
pre-cast concrete elements, some of which were pre-stressed.
The Kendal Building is unique in the sense
that a further entirely independent floor was added in the
mid 1990’s. This was provided with an independent
steel frame with hollow section columns placed around the
outside of the building. The building was also linked to
the adjacent Leighton Building by a three storey link corridor
which cantilevered into the Kendal Building.
Access to the site from the Leighton Building
was prevented by blocking off each corridor at the position
of the fire doors.
Access to the staff canteen and Maudland
Building was via a scaffolded walkway located adjacent to
the canteen.
Entry to the remaining site was prevented
by erecting a hoarding in the lobby area.
Due to the highly sensitive location of the project stringent
measure had to be implemented to control noise, dust and
vibration.
Furthermore the works necessitated a very
tight programme as the demolition had to be completed within
12 weeks to allow for the installation of the new fire escape
in time for the imminent return of the students.
One of the most challenging aspects of
the contract was the separation of the link corridor building
and the protection of the electrical switch room which served
the other campus buildings.
This necessitation careful hand separation
techniques and the utilisation of a mobile crane which systematically
lifted out the pre cast panels. The main structure was demolished
using Connell Brothers 28 hydraulic demolition excavator.
Careful planning and liaison are also playing
a crucial role in the smooth running of the contract. As
principal contractor Connell brothers had to co –
ordinate, oversee and control the operations of over a dozen
sub contractors who were often working concurrently on site.
This included mechanical and electrical installation, piling,
steel erection, cladding, pre cast concrete, finishings,
and tarmacing to name but a few.
Working closely with the University was
also essential. Regular safety and progress meetings are
held with numerous departments within the University to
alleviate any concerns that they may have as the works proceed.
The vast experience of university projects
carried out by Connell Brothers has paid dividends. The
technical manager in charge of the works Mr Chris Graham
said, “This project has been very interesting due
to the unique design of the building which in a sense makes
it two buildings in one. Another aspect which has been of
interest is the large amount of building works which we
have had to manage.”
CASE
STUDIES - HOME
- EMAIL
|