|
The project commissioned by York
University consisted of the demolition and the safe dismantling
of the University Landmark Water Tower, and the demolition
of the Chemistry Laboratory Block D. The Tower (seen above)
comprised of an inverted 21metre diameter conical tank which
was made up of 32 pre cast concrete petals each weighing
8.5 tonne. The Overall Height of the Tower was approximately
28 metres, the central core stem being 2.3 metres diameter
.
One of the main features of the project
was its environmental surroundings. The Tower sat in a quadrangle
which is in the middle of the Chemistry Department at the
University. The Chemistry Department is a collection of
single and two storey structures containing operational
lecturing, teaching and research facilities. Covered Walkways
surround the perimeter of the quadrangle and are used by
students, staff and visitors on a daily basis. One of the
main challenges facing Connell Brothers was to maintain
access to the department throughout the proposed works,
with as little disruption to every day life at the University
as possible. As can be seen by the photograph below, due
to the extremely condensed environment of the project, safety
was of paramount importance. Also with the village of Heslington
in close proximity there were traffic and access considerations
which had to be taken into account. Connell Brothers adopted
an innovative approach from early Tender Stage of the Project
and throughout the execution of the works.
Close Liaison with the University was an
essential factor to the smooth running of this project.
The prime concerns of the university were those of noise,
dust and vibration which can effect the workings of instruments
within the laboratory. Connell Brothers kept the use of
percussive tools to a minimum in order to limit vibration
levels. Regular background noise readings were taken to
ensure that noise levels were kept to a minimal level. Dust
arising from the operation was also a main factor for consideration
and the Project included implementing a strict regime of
dust control measures. Also specialist filters were procured
and fitted to the Laboratories Air inlet systems to prevent
dust contamination, which would seriously effect sensitive
experiments taking place inside the buildings. It was also
essential to provide protection for gullies and drains to
prevent dust/debris entry. This was necessary as local lagoons
contained rare Coy Carp and could not be polluted by any
means. Further liaison was also required with regards to
working hours. Works had to be liased and phased around
the Chemistry Departments busy experimental schedule to
take account of any possible emissions resulting from the
experiments.
The demolition of Block D was done by a
specialist excavator fitted with a hydraulic grapple attachment.
This part of the project was complicated by the large amounts
of asbestos located in the structure. This required the
specialist removal under all current legislation prior to
the structure being demolished. The Demolition of the Block
enabled the crane to be located in the footprint of the
building to allow careful dismantling of the petals. It
also allowed access at a future date within the contract
for the high reach machine to demolish the remaining stem.
There was a degree of uncertainty surrounding
the demolition of the pre cast structure of the Tower as
it had been subject to deterioration since erection. At
Tender stage, the 32 petals forming the bowl of the water
tank were described as each individually being restrained
by wire ropes to the central core. Upon opening up the works,
it was found that the stated 32 restraining Ropes had only
been used during the construction of the bowl and had been
removed, therefore the petals of the tank were gaining support
from the ring beams.
The lack of the restraining ropes, contrary
to that described in the tender documents necessitated Connell
Brothers to carry out a full structural reappraisal of the
dismantling techniques to be employed. On completion of
the appraisal, it was decided that 32 restraining ropes
to the outer edge of the petals and a further 32 restraining
ropes to the inner edge of the ring beam would require installing
to enable safe dismantling of the petals. A proactive approach
was adopted to the immediate sourcing, fabrication and installation
of the ropes. A fully designed structural scaffold was erected
to take the self-weight of the petals.
Once the scaffold and restraining ropes
were installed, a planned sequence of dismantling was undertaken
by cutting the petals in half at the point of intersection
of the central ring beam and lifting in sequence therefore
maintaining the overall integrity of the structure. Repetitive
lifting operations were carried out by removing the outer
sections of the petals in the first phase and inner sections
of the petals in the second phase, leaving the stem exposed
along its full height.
The top section of the stem weighing 16
tonnes was a heavily reinforced structure containing the
64 holes, which were incorporated during construction for
restraining the petals. The top section was separated from
the reminder of the stem and lifted down to ground level
in one operation. Once at ground level excavators fitted
with hydraulic attachments reduced the structure by munching
down.
With all high level works complete, the
supporting scaffold was taken down to enable access for
the Long Reach Machine. With protection still in place to
the covered walkways and the entire quadrangle secured as
an exclusion zone the munching down of the remaining stem
commenced. The stem was successfully removed within a 6
hour period, thus minimizing disruption to the campus users.
The Management of the Project was carried
out in close liaison with Faber Maunsell and the University.
The Project was headed by Mr. J. Connell, Projects Director,
with Site Supervisors, Foremen, Safety Advisor, Structural
Consultants, Monitoring Consultants and a team of highly
trained (CITB) demolition Operatives and machine Operators.
The Management called for regular Safety Audits of the site,
weekly Tool Box Talks with regards to safety, regular Method
Statement Induction courses for all Operatives on site,
fortnightly Progress and Safety Meetings with Faber Maunsell.
Regular auditing was undertaken to ensure that the Project
Management procedures were followed. The project took 20
weeks to complete and throughout the works, safety to all
Personnel on site and the General Public was of paramount
importance. A strict regime of safety procedures was implemented
and Connell Brothers can report that no notifiable incidents
occurred throughout the 20 week project period.
.
CASE
STUDIES - HOME
- EMAIL
|